Solar Photovoltaic and Energy Storage Solution for DRD Gold Mine
For the proposed solar photovoltaic (PV) and energy storage solution at DRD Gold Mine, we undertook the detailed design, supply, and installation of medium-voltage (MV) grid connection works. This ambitious project involved establishing MV infrastructure and electric transmission lines, enabling the transmission of electricity from a proposed 60 MW solar PV plant to the mine’s key consumers—the processing plant and tailings dam pumping system.